Scout Moor Wind Farm Images May 2008
11th May 2008
<-- Index | Showing 1-120 of 325 pictures | Next -->
My first visit of May was on the 3rd, when I could see that the first three sections of Turbine 13 had been completed. I thought that this would mean that I would finally get a chance to photograph one of the nacelles being fitted, and I made plans to visit again on the next working day. Because of the Bank Holiday this was on the 6th of May, and with an early start, I was soon over at the site and all set up ready to get my shot. Yet again it wasn't to be, and in spite of it being a lovely sunny day, the strong east wind prevented any lifting from being done, and yet again my efforts to get this shot was thwarted.

With all the work now taking place at the western side of the site near to Edenfield this means a very long walk from here, and I wasn't able to get over again until Saturday the 10th. On Saturdays I often visit Irwell Vale and Ewood Bridge on the East Lancashire Railway, and since they are only a couple of miles from where the site is, it allowed me to kill two birds with one stone and visit both of them. This time I could see that work was now completed on Turbine 13, and construction had moved on to the site of Turbine 24. I was hoping that I might get another chance with this one weather permitting, and hopefully would finally succeed before I managed to burn out yet another pair of walking boots! smile 

Well I was wrong, yet again the wind ruined my plans, and on a visit on May 12th I saw the work on Turbine 24 held up by the strong east wind. This wasn't helped by a problem with the large crane, which kept it out of action for most of the morning, with the winds worsening as the day progressed. The trip wasn't a total loss though, and I got some nice shots of the crane being repaired. An added bonus was seeing an erection team arrive with the two weather masts for the site, and I was able to get some shots of these being unloaded. The one near the top of the site was left on the ground in sections, but the one at the lower end was put together, but remained in one piece on the ground when the team finished for the day. Another mobile crane was brought into unload and erect the sections of the lattice tower, and this belonged to a company called John Sutch Cranes. The tower sections arrived in a juggernaut with DSV on the side, the original trailer showing a German registration number.

Another visit on the 16th of May saw the winds finally drop, and the weather mast at the bottom of the site erected, and also the blades fitted to Turbine 24. Unfortunately I missed some of the lifting of the weather mast, as the crane was initially parked up at the site of the upper mast, and when it suddenly departed for the one at the bottom of the site I found myself facing a two mile walk to get there. The mast was already in the vertical position by the time I arrived on scene, but I will hopefully do better when the upper one is raised.

The next visit was on the 19th of May when at long last I was finally able to get some shots of a Nacelle being lifted and fitted. These shots are numbered in the range Scout732 to Scout 813. The east winds continue to cause problems, but in spite of being breezy that day, the winds were just low enough for the cranes to still operate safely.

22nd of May saw yet another visit, and this time it was to see the remaining weather mast erected. This time two cranes arrived on site, and duly unloaded a replacement section for the mast at the southern end of the site to replace one that had been damaged during the lifting. In spite of the bright sunny day, the strong east wind just continued to blow hard all day, and no lifting was possible unfortunately. This was doubly annoying after yet another five mile hike, and as yet I have no idea when another attempt will be made. Image numbers scout814 to scout855 show the cranes and vehicles used during the abortive attempt.

Along came the late May Bank Holiday, and thanks to an illegal rave held at the nearby disused Ding Quarry, some of the morons attending decided it would be a good idea to break into Turbine 19 and use it as a toilet. This resulted in a police raid and a lot of publicity in the local newspaper and TV news, and the following week security grills were noted being fitted to all of the doors (scout869/870.jpg).

After several days of poor weather and high winds the engineers returned again to finish the weather masts on the 30th of May, and after another early start and long trek, work began on fitting the mast at Higher Hill (scout887-scout895.jpg). After this was completed (and the lift went very smoothly this time with the two cranes on site), the original mast down at the Knowl Moor end of the site was lowered so that the damaged section could be replaced. The work went well, and in spite of the grey, wet and miserable conditions I was able to get some interesting shots of proceedings (about 250 in all, but don't worry I've only posted a few of them here! scout871-scout886.jpg).

The finished mast.
The finished mast.
1250x897
scout895.jpg
The base section.
The base section.
1250x834
scout886.jpg
Solar panel for power
Solar panel for power
1250x1044
scout894.jpg
Completed base with 'Wally Screen' erected around it.
Completed base with 'Wally Screen' erected around it.
1250x841
scout893.jpg
The big crane departs
The big crane departs
1250x834
scout883.jpg
The small crane departs
The small crane departs
1250x845
scout882.jpg
The 'Wally Screen' is replaced.
The 'Wally Screen' is replaced.
1250x907
scout881.jpg
Back down again
Back down again
1250x1240
scout880.jpg
A little work on the anenometers
A little work on the anenometers
1250x957
scout879.jpg
The engineer scales the mast
The engineer scales the mast
1250x1209
scout878.jpg

1250x834
scout885.jpg

1250x834
scout884.jpg
The mast is lowered onto its base.
The mast is lowered onto its base.
1250x904
scout877.jpg
The mast is lifted again
The mast is lifted again
950x1262
scout876.jpg
The new section is fitted.
The new section is fitted.
1250x909
scout875.jpg
The damaged section is lifted out.
The damaged section is lifted out.
1250x861
scout874.jpg
The damaged section is removed
The damaged section is removed
1250x831
scout873.jpg
The mast is lowered
The mast is lowered
1250x874
scout872.jpg
Weather Mast on Knowl Moor
Weather Mast on Knowl Moor
1250x862
scout871.jpg
The sling is removed by the engineer.
The sling is removed by the engineer.
1250x916
scout892.jpg
Nearly done!
Nearly done!
1250x907
scout891.jpg
Almost vertical
Almost vertical
1250x1352
scout889.jpg
Onto the mountings
Onto the mountings
1250x949
scout890.jpg
The new mast is raised
The new mast is raised
950x1098
scout888.jpg
Weather mast at Higher Hill
Weather mast at Higher Hill
1250x855
scout887.jpg
Shortly afterwards reinforced grills were fitted over the doors, plus lots of warning stickers.
Shortly afterwards reinforced grills were fitted over the doors, plus lots of warning stickers.
1250x834
scout870.jpg
THis turbine was vandalised during the May Bank Holiday by some morons from an illegal rave held in the nearby Ding Quarry.
THis turbine was vandalised during the May Bank Holiday by some morons from an illegal rave held in the nearby Ding Quarry.
1250x924
scout869.jpg
The nuts and bolts are unloaded
The nuts and bolts are unloaded
1250x866
scout868.jpg
The transformer is lowered onto the base
The transformer is lowered onto the base
1250x842
scout867.jpg
Work starts on Turbine 26
Work starts on Turbine 26
1250x834
scout866.jpg

1250x834
scout865.jpg
Colletts Transporter
Colletts Transporter
1250x834
scout864.jpg
Colletts Transporter brings in the parts for Turbine 26
Colletts Transporter brings in the parts for Turbine 26
1250x883
scout863.jpg
Knowl Moor weather mast
Knowl Moor weather mast
1250x1925
scout862.jpg
The new section awaits fitting
The new section awaits fitting
1250x854
scout861.jpg
The damaged section can be seen at the top of the mast
The damaged section can be seen at the top of the mast
1250x1068
scout860.jpg
Weather mast on Knowl Moor
Weather mast on Knowl Moor
1250x881
scout859.jpg
The Nordex compound
The Nordex compound
1250x834
scout853.jpg

1250x834
scout855.jpg

1250x873
scout852.jpg

1250x857
scout851.jpg
New tower section arrives
New tower section arrives
1250x942
scout850.jpg

1250x899
scout849.jpg

1250x915
scout848.jpg

1250x921
scout847.jpg

1250x872
scout846.jpg

1250x834
scout845.jpg

1250x869
scout844.jpg

1250x913
scout843.jpg

1250x885
scout842.jpg

1250x855
scout841.jpg

1250x876
scout840.jpg

950x1171
scout839.jpg

1250x924
scout838.jpg

1250x884
scout835.jpg

1250x929
scout837.jpg

1250x859
scout836.jpg

950x1239
scout854.jpg

950x1263
scout834.jpg

1250x910
scout833.jpg

1250x889
scout832.jpg

1250x913
scout831.jpg

1250x882
scout830.jpg

1250x913
scout829.jpg

1250x906
scout828.jpg

1250x929
scout827.jpg

1250x907
scout826.jpg

1250x899
scout825.jpg

1250x910
scout824.jpg

1250x956
scout823.jpg

1250x975
scout822.jpg

1250x932
scout821.jpg

1250x858
scout820.jpg

1250x893
scout819.jpg

1250x888
scout818.jpg
The new section of weather masr arrives
The new section of weather masr arrives
1250x871
scout817.jpg

1250x872
scout816.jpg
The cranes arrive to make another attempt at raising the weather mast
The cranes arrive to make another attempt at raising the weather mast
1250x834
scout815.jpg

1250x862
scout814.jpg

1250x834
scout732.jpg

1250x914
scout813.jpg

1250x834
scout812.jpg

1250x834
scout811.jpg

1250x859
scout810.jpg

1250x903
scout809.jpg
The first blade is lifted on Turbine 22
The first blade is lifted on Turbine 22
1250x1664
scout808.jpg

1250x894
scout807.jpg

1250x855
scout806.jpg

1250x834
scout805.jpg

1250x894
scout804.jpg

1250x860
scout803.jpg

1250x844
scout802.jpg
The blades arrive
The blades arrive
1250x912
scout801.jpg

1250x852
scout800.jpg

1250x836
scout799.jpg

1250x908
scout798.jpg

1250x1084
scout797.jpg

1250x1122
scout796.jpg

1250x846
scout795.jpg

1250x867
scout794.jpg

1250x869
scout793.jpg

1250x911
scout792.jpg

1250x894
scout791.jpg
The hub is lifted
The hub is lifted
1250x952
scout790.jpg

1250x911
scout789.jpg

1250x897
scout788.jpg

1250x850
scout787.jpg

1250x1019
scout786.jpg

1250x969
scout785.jpg

1250x915
scout784.jpg

1250x901
scout783.jpg

1250x855
scout782.jpg

1250x891
scout781.jpg

1250x958
scout780.jpg

1250x895
scout779.jpg
The generator is unloaded
The generator is unloaded
1250x927
scout778.jpg

1250x916
scout777.jpg

1250x895
scout776.jpg

1250x925
scout775.jpg

950x1316
scout774.jpg